Ladbrokes

BACKGROUND

Ladbrokes had experienced rapid growth which required a move to a larger location to cater for a significant increase in staff. They engaged Power On Australia to audit and manage their Power Quality needs during the relocation of the Trading and Client Services teams.

RESULTS

In 4 weeks, POA designed, built and installed a brand-new Mains & Sub Switchboard. They also devised a 30 kva Battery Backup Solution to guarantee mains supply to critical IT equipment in the event of a power outage.

“A real feather in their cap was their ability to complete all of the engineering and electrical works within the 4 week timeframe and on budget.”
Peter Stevenson, GM – Client Services
Ladbrokes

Back to Case Studies

SUMMARY

asd

RESULTS

asd

PROJECT DETAILS

The entire project ran almost seamlessly. Their communication throughout was beyond diligent – particularly considering they had to deal with multiple parties.

Power On Australia worked in with and managed 2 electrical contractors, a builder and a landlord with the utmost professionalism.

Boyd Lockett, the owner, was approachable, flexible and hands on throughout the project. It’s rare to have the owner of a company take such a direct role.

The minute there was an issue, Boyd was on the phone or out onsite. Potential problems were resolved quickly and without fuss.

Peter Stevenson

General Manager for Client Services